Battery Storage

Anchor Lane Energy Centre

Land adj to Birmingham Canal S, Anchor Lane, Anchor Bridge, Bilston, West Midlands, West Midlands, WV14 9NE

Anchor Lane Energy Centre is a 4 MW battery storage project in West Midlands. The applicant or operator on record is Suncredit. It is recorded as operational since October 2020. The determining authority is Wolverhampton, reference 18/01234/FUL.…

Operational Β· Since 2020
Project stageOperating
  1. PlanningOct 2018 (completed)
  2. ConsentedAug 2021 (completed)
  3. ConstructionAug 2020 (completed)
  4. OperatingOct 2020 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2023-03-31.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

4.000 MW
Power Capacity
2020
Commissioned

πŸ“‹ Project Overview

Anchor Lane Energy Centre is a 4 MW battery storage project in West Midlands. The applicant or operator on record is Suncredit. It is recorded as operational since October 2020. The determining authority is Wolverhampton, reference 18/01234/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)4.000 MW
Battery chemistryCo-located with RE

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperSuncredit
Owner / operatorSuncredit
Year consented2021
Construction started2020
Commissioned / target2020
LocationLand adj to Birmingham Canal S, Anchor Lane, Anchor Bridge, Bilston, West Midlands, West Midlands, WV14 9NE
RegionWest Midlands
Coordinates52.5521163Β°N, 2.0905696Β°W

Additional published register fields

Registered technologyBattery
Storage Co-location REPD Ref ID6796

πŸ“… Project Timeline

2018-10-19
2021-08-13
2020-08-01
2020-10-01