Allers Wastewater Treatment Works, Barrie Road, East Kilbride, Glasgow City, G74 3XZ
Allers Wastewater Treatment Works, Barrie Road - Solar Pv Array is a 0.24 MW solar farm project in Scotland. The applicant or operator on record is Scottish Water National Operations Control Centre. It is recorded as operational since January 2025. The determining authority is Soβ¦
OperationalΒ· Since 2025
Project stageOperating
PlanningFeb 2024 (completed)
ConsentedApr 2024 (completed)
ConstructionSep 2024 (completed)
OperatingJan 2025 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2025-02-25.
Registered planning capacity; not measured generation.
Allers Wastewater Treatment Works, Barrie Road - Solar Pv Array is a 0.24 MW solar farm project in Scotland. The applicant or operator on record is Scottish Water National Operations Control Centre. It is recorded as operational since January 2025. The determining authority is South Lanarkshire, reference P/24/0118.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
0.240 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Scottish Water National Operations Control Centre
Owner / operator
Scottish Water National Operations Control Centre
Year consented
2024
Construction started
2024
Commissioned / target
2025
Location
Allers Wastewater Treatment Works, Barrie Road, East Kilbride, Glasgow City, G74 3XZ