Land At A'Cruach
Kilmichael Forest
West Of Minard
Argyll, Strathclyde
A'Chruach (Phase 1) is a 48.3 MW onshore wind project in Scotland. The applicant or operator on record is Infinis (formerly Novera Energy). It is recorded as operational since June 2016. The determining authority is Argyll and Bute, reference 11/02520/PP.β¦
OperationalΒ· Since 2016
Official register: July 2026
Recorded status: Operational. Source record updated 2017-04-04.
Registered planning capacity; not measured generation.
A'Chruach (Phase 1) is a 48.3 MW onshore wind project in Scotland. The applicant or operator on record is Infinis (formerly Novera Energy). It is recorded as operational since June 2016. The determining authority is Argyll and Bute, reference 11/02520/PP.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
48.300 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Infinis (formerly Novera Energy)
Owner / operator
Infinis (formerly Novera Energy)
Year consented
2012
Construction started
2015
Commissioned / target
2016
Location
Land At A'Cruach
Kilmichael Forest
West Of Minard
Argyll, Strathclyde