Offshore Wind

Inch Cape

North Sea, 15–22 km off the Angus coast, near Montrose

Inch Cape is a 1.08 GW project off the Angus coast, developed by a partnership of Red Rock Renewables and TotalEnergies. It won a CfD in Allocation Round 4 in 2022 at Β£37.35/MWh β€” part of the same round that saw record volumes awarded at low prices. Located near the existing S…

Consented / Approved Β· Target 2028
1,080 MW
Installed Capacity
72
Turbines
900k
Homes Powered
4,000 GWh
Est. Annual Output
2028
Target Date

πŸ“‹ Project Overview

Inch Cape is a 1.08 GW project off the Angus coast, developed by a partnership of Red Rock Renewables and TotalEnergies. It won a CfD in Allocation Round 4 in 2022 at Β£37.35/MWh β€” part of the same round that saw record volumes awarded at low prices. Located near the existing Seagreen wind farm and sharing grid infrastructure, it forms an important part of Scotland's growing offshore wind capacity.

Site Schematic

β—„ SHORE (~15 km) NORTH SEA / NORTH SEA (SCOTLAND) Turbine (15 MW class (TBC)) Export cable

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

⚑ Key Facts

β†’ 1,080 MW β€” 72 turbines off the Angus coast
β†’ Won CfD AR4 at Β£37.35/MWh β€” record pricing at the time
β†’ TotalEnergies acquired 70% stake from Red Rock in 2021
β†’ Shares grid corridor with Seagreen wind farm
β†’ ~900,000 homes powered

πŸ”§ Technical Specifications

Capacity (MW)1,080 MW
No. of turbines/units72
Turbine / unit model15 MW class (TBC)
Unit capacity15 MW each
Foundation typeMonopile (XL)
Water depth25–60 m
Distance from shore15 km
Site area150 kmΒ²
Annual output4,000 GWh/year
Homes powered900,000 homes

πŸ”Œ Grid Connection & Infrastructure

Grid connection pointTealing substation, Angus β€” shared with Seagreen cluster
Voltage220 kV
CfD heldYes β€” Allocation Round AR4Β£37.35/MWh (2012 prices)

🏒 Development & Ownership

DeveloperRed Rock Renewables / TotalEnergies
Owner / operatorRed Rock Renewables (30%) / TotalEnergies (70%)
Year consented2017
Construction started2025
Commissioned / target2028
LocationNorth Sea, 15–22 km off the Angus coast, near Montrose
RegionNorth Sea (Scotland)
Coordinates56.65Β°N, 2.35Β°W

πŸ“… Project Timeline

🌿 Environmental & Planning

EIA included extensive seabird surveys for the Angus coast and sandeel surveys. The site is near the Firth of Tay and Eden Estuary SPA.