β France power stations atlas
Octary Global Β· France Β· Solar
NIVOUV01 - ADP 01 DE LA CENTRALE SOLAIRE PHOTOVOLTAIQUE DE NIVOUVILLE
ChΓ’teaudun Β· Centre-Val de Loire Β· Operating
88.00
MW installed as reported
2025-11-28
Commissioning date, if provided

Engineering and capacity
- Technology
- Solar
- Detailed technology
- PhotovoltaΓ―que
- Fuel
- Not supplied
- Installed power
- 88.000 MW
- Storage energy
- Not supplied; source units must be checked
- Voltage
- 90 kV
Location and responsible parties
- Commune
- ChΓ’teaudun
- Department
- Eure-et-Loir
- Region
- Centre-Val de Loire
- Location accuracy
- Commune only; exact site not verified
- Owner
- Not verified
- Operator
- Not verified
- Network manager
- RTE
Project timeline
- Commissioned
- 2025-11-28
- Connected
- 2025-08-12
- Disconnected
- Not reported
- Reported status
- Operating
Connection and disconnection dates do not independently establish complete station construction or decommissioning history.
Technology graphics
Technology illustrations are reusable from Octary's UK atlas and are schematic, not photographs of this particular plant.

Source record
- EIC identifier
- 17W000002173846Z
- Source family
- fr-rte-register