Onshore Wind

Kilgallioch Windfarm (Extension)

High Eldrig, land 12 km NW of Kirkcowan, SE of Kilgallioch Windfarm, Dumfries and Galloway

Kilgallioch Windfarm (Extension) is a 50.4 MW onshore wind project in Scotland. The applicant or operator on record is ScottishPower Renewables. It is recorded as under construction since June 2025. The determining authority is Scottish Government (S36), reference ECU00001996.…

Under Construction
Project stageUnder construction
  1. PlanningDec 2019 (completed)
  2. ConsentedDec 2021 (completed)
  3. ConstructionJun 2025 (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Under Construction.

Official register: July 2026

Recorded status: Under Construction. Source record updated 2025-08-05.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

50.400 MW
Registered Capacity

πŸ“‹ Project Overview

Kilgallioch Windfarm (Extension) is a 50.4 MW onshore wind project in Scotland. The applicant or operator on record is ScottishPower Renewables. It is recorded as under construction since June 2025. The determining authority is Scottish Government (S36), reference ECU00001996.

Site Schematic

SCOTLAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)50.400 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperScottishPower Renewables
Owner / operatorScottishPower Renewables
Year consented2021
Construction started2025
LocationHigh Eldrig, land 12 km NW of Kirkcowan, SE of Kilgallioch Windfarm, Dumfries and Galloway
RegionScotland
Coordinates54.9937365Β°N, 4.7371009Β°W

Additional published register fields

Registered technologyWind Onshore
Storage Co-location REPD Ref ID7851
CfD Allocation RoundAR4
CfD Capacity (MW)51.3
Turbine Capacity (MW)5.6
No. of Turbines9
Height of Turbines (m)180

πŸ“… Project Timeline

2019-12-16
2021-12-08
2025-06-01