Land 330M SE Of, Birch View, Auchindarroch Duror, Appin, Strathclyde, Highland, PA38 4BS
Duror 2 Hydro Scheme is a 0.4 MW conventional hydro project in Scotland. The applicant or operator on record is H2O Power Generation. It is recorded as under construction since July 2020. The determining authority is Highland, reference 18/05283/FUL.β¦
Under Construction
Project stageUnder construction
PlanningNov 2018 (completed)
ConsentedMar 2019 (completed)
ConstructionJul 2020 (current stage)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Under Construction.
Official register: July 2026
Recorded status: Under Construction. Source record updated 2020-07-29.
Registered planning capacity; not measured generation.
Duror 2 Hydro Scheme is a 0.4 MW conventional hydro project in Scotland. The applicant or operator on record is H2O Power Generation. It is recorded as under construction since July 2020. The determining authority is Highland, reference 18/05283/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
0.400 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
H2O Power Generation
Owner / operator
H2O Power Generation
Year consented
2019
Construction started
2020
Location