π Project Overview
Douglas West Wind Farm (extension) is a 78 MW onshore wind project in Scotland. The applicant or operator on record is ScottishPower Renewables (UK) Limited. It is recorded as under construction since June 2024. The determining authority is Scottish Government (S36), reference ECU00001836.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
| Capacity (MW) | 78 MW |
π Grid Connection & Infrastructure
π’ Development & Ownership
| Developer | ScottishPower Renewables (UK) Limited |
| Owner / operator | ScottishPower Renewables (UK) Limited |
| Year consented | 2021 |
| Construction started | 2024 |
| Location | Douglas West and Dalquhandy, F, Lesmahagow, Site West of Junction 11 of M7, Lanark,, Strathclyde, ML11 0NN |
| Region | Scotland |
| Coordinates | 55.5873575Β°N, 3.8901039Β°W |