πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Conventional Hydro

Dalchonzie

Dalchonzie, Tayside

Dalchonzie is a 4 MW conventional hydro project in Scotland. The applicant or operator on record is Scottish and Southern Energy (SSE). It is recorded as operational since January 1958. The determining authority is Perth and Kinross.…

Operational Β· Since 1958
Official register: July 2026

Recorded status: Operational. Source record updated 2015-12-17.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

4.000 MW
Registered Capacity
1958
Commissioned

πŸ“‹ Project Overview

Dalchonzie is a 4 MW conventional hydro project in Scotland. The applicant or operator on record is Scottish and Southern Energy (SSE). It is recorded as operational since January 1958. The determining authority is Perth and Kinross.

Site Schematic

UPPER RES. LOWER RES. PENSTOCK TAILRACE GEN. GRID HEAD: ?m Β· POWER: 4.000 MW Β· ? turbines

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)4.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperScottish and Southern Energy (SSE)
Owner / operatorScottish and Southern Energy (SSE)
Commissioned / target1958
LocationDalchonzie, Tayside
RegionScotland
Coordinates56.3733778Β°N, 4.0411204Β°W

Additional published register fields

Registered technologySmall Hydro

πŸ“… Project Timeline

1958-01-01