Land To The South Of Bruxiehil, St. Fergus, Peterhead, Aberdeenshire
Bruxiehall Farm is a 2 MW solar farm project in Scotland. The applicant or operator on record is Bruxiehill Wind Energy. It is recorded as under construction since September 2018. The determining authority is Aberdeenshire, reference APP/2015/3060.β¦
Under Construction
Project stageUnder construction
PlanningSep 2015 (completed)
ConsentedNov 2015 (completed)
ConstructionSep 2018 (current stage)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Under Construction.
Official register: July 2026
Recorded status: Under Construction. Source record updated 2019-01-24.
Registered planning capacity; not measured generation.
Bruxiehall Farm is a 2 MW solar farm project in Scotland. The applicant or operator on record is Bruxiehill Wind Energy. It is recorded as under construction since September 2018. The determining authority is Aberdeenshire, reference APP/2015/3060.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
2.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Bruxiehill Wind Energy
Owner / operator
Bruxiehill Wind Energy
Year consented
2015
Construction started
2018
Location
Land To The South Of Bruxiehil, St. Fergus, Peterhead, Aberdeenshire