πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Onshore Wind

Ballinderry Road

Lands 217m East Of, 106 Ballinderry Road, Aughacarnan, Lisburn,, Co. Antrim, BT28 2NW

Ballinderry Road is a 0.3 MW onshore wind project in Northern Ireland. The applicant or operator on record is Private Developer. Planning permission has been granted as of November 2020 and it is awaiting construction. The determining authority is Lisburn and Castlereagh, referen…

Consented / Approved
Project stageConsented
  1. PlanningNov 2019 (completed)
  2. ConsentedNov 2020 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2021-02-07.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

0.300 MW
Registered Capacity

πŸ“‹ Project Overview

Ballinderry Road is a 0.3 MW onshore wind project in Northern Ireland. The applicant or operator on record is Private Developer. Planning permission has been granted as of November 2020 and it is awaiting construction. The determining authority is Lisburn and Castlereagh, reference LA05/2019/1212/F.

Site Schematic

NORTHERN IRELAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)0.300 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperPrivate Developer
Owner / operatorPrivate Developer
Year consented2020
LocationLands 217m East Of, 106 Ballinderry Road, Aughacarnan, Lisburn,, Co. Antrim, BT28 2NW
RegionNorthern Ireland
Coordinates54.537168Β°N, 6.1602432Β°W

Additional published register fields

Registered technologyWind Onshore
No. of Turbines1
Height of Turbines (m)52
Are they re-applying (New REPD Ref)7495

πŸ“… Project Timeline

2019-11-27
2020-11-10