Aurora Solar Farm is a 32 MW solar farm project in South East. The applicant or operator on record is Low Carbon UK Solar Investment Company. It is recorded as under construction since April 2021. The determining authority is West Oxfordshire, reference 19/02516/FUL.…

Under Construction
Project stageUnder construction
  1. PlanningSep 2019 (completed)
  2. ConsentedFeb 2020 (completed)
  3. ConstructionApr 2021 (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Under Construction.

Official register: July 2026

Recorded status: Under Construction. Source record updated 2023-03-23.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

32.000 MW
Registered Capacity

πŸ“‹ Project Overview

Aurora Solar Farm is a 32 MW solar farm project in South East. The applicant or operator on record is Low Carbon UK Solar Investment Company. It is recorded as under construction since April 2021. The determining authority is West Oxfordshire, reference 19/02516/FUL.

Site Schematic

SUBSTATION ? ha Β· 32 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)32.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperLow Carbon UK Solar Investment Company
Owner / operatorLow Carbon UK Solar Investment Company
Year consented2020
Construction started2021
LocationTwelve Acre Farm, Chilbridge Road, Eynsham, Witney,, Oxfordshire, OX29 4BH
RegionSouth East
Coordinates51.7809774Β°N, 1.4035779Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Storage Co-location REPD Ref ID7385
Mounting Type for SolarGround
Solar Site Area (sqm)634000

πŸ“… Project Timeline

2019-09-24
2020-02-10
2021-04-26