Solar Farm

AMBLESTON SOLAR PANELS

Television Transmitter Centre, Ambleston, Haverfordwest, Dyfed, SA61, Dyfed

AMBLESTON SOLAR PANELS is a 6 MW solar farm project in Wales. The applicant or operator on record is Arqiva Ltd. It is recorded as operational since January 2012. The determining authority is Pembrokeshire, reference 11/0104/PA.…

Operational Β· Since 2012
Project stageOperating
  1. PlanningJun 2011 (completed)
  2. ConsentedAug 2011 (completed)
  3. ConstructionOct 2011 (completed)
  4. OperatingJan 2012 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2014-01-29.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

6.000 MW
Registered Capacity
2012
Commissioned

πŸ“‹ Project Overview

AMBLESTON SOLAR PANELS is a 6 MW solar farm project in Wales. The applicant or operator on record is Arqiva Ltd. It is recorded as operational since January 2012. The determining authority is Pembrokeshire, reference 11/0104/PA.

Site Schematic

SUBSTATION ? ha Β· 6 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)6.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperArqiva Ltd
Owner / operatorArqiva Ltd
Year consented2011
Construction started2011
Commissioned / target2012
LocationTelevision Transmitter Centre, Ambleston, Haverfordwest, Dyfed, SA61, Dyfed
RegionWales
Coordinates51.8991808Β°N, 4.8664565Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Solar Site Area (sqm)4900

πŸ“… Project Timeline

2011-06-16
2011-08-11
2011-10-24
2012-01-25