π Project Overview
Sutton Bridge Solar Farm is a 49.9 MW solar farm project in East Midlands. The applicant or operator on record is EDF Energy Renewables. It is recorded as operational since April 2024. The determining authority is South Holland, reference H18-1126-20.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
| Capacity (MW) | 50 MW |
π Grid Connection & Infrastructure
π’ Development & Ownership
| Developer | EDF Energy Renewables |
| Owner / operator | EDF Energy Renewables |
| Year consented | 2021 |
| Construction started | 2022 |
| Commissioned / target | 2024 |
| Location | Sutton Bridge Solar Farm, Centenary Way, Sutton Bridge, Spalding, Lincolnshire, PE12 9TF |
| Region | East Midlands |
| Coordinates | 52.7571802Β°N, 0.1931442Β°E |