π Project Overview
Maesgwyn is a 26 MW onshore wind project in Wales. The applicant or operator on record is Pennant Wind Energy Ventures. It is recorded as operational since April 2011. The determining authority is Neath Port Talbot, reference P/2006/1261.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
| Capacity (MW) | 26 MW |
π Grid Connection & Infrastructure
π’ Development & Ownership
| Developer | Pennant Wind Energy Ventures |
| Owner / operator | Pennant Wind Energy Ventures |
| Year consented | 2009 |
| Construction started | 2010 |
| Commissioned / target | 2011 |
| Location | Maesgwyn, Glynneath, Neath, West Glamorgan. SA11, West Glamorgan |
| Region | Wales |
| Coordinates | 51.7364756Β°N, 3.6595544Β°W |