Land at Upper Clayhill Farm is a 4.9 MW solar farm project in South East. The applicant or operator on record is Lightsource Renewable Energy. It is recorded as operational since December 2015. The determining authority is Lewes, reference LW/14/0771.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
| Capacity (MW) | 5 MW |
π Grid Connection & Infrastructure
π’ Development & Ownership
| Developer | Lightsource Renewable Energy |
| Owner / operator | Lightsource Renewable Energy |
| Year consented | 2014 |
| Construction started | 2015 |
| Commissioned / target | 2015 |
| Location | Upper Clayhill Farm, Uckfield Road, Ringmer, Lewes, East Sussex, BN8 5RR |
| Region | South East |
| Coordinates | 50.9159194Β°N, 0.0553516Β°E |