π Project Overview
Higher Knapp Farm is a 1.5 MW solar farm project in South West. The applicant or operator on record is Lightsource Renewable Energy. It is recorded as operational since March 2013. The determining authority is Somerset, reference 24/12/0039.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
| Capacity (MW) | 2 MW |
π Grid Connection & Infrastructure
π’ Development & Ownership
| Developer | Lightsource Renewable Energy |
| Owner / operator | Lightsource Renewable Energy |
| Year consented | 2013 |
| Construction started | 2013 |
| Commissioned / target | 2013 |
| Location | Higher Knapp Farm, Knapp, Taunton, Somerset, TA3 6AY, Somerset |
| Region | South West |
| Coordinates | 51.0193391Β°N, 2.996189Β°W |