π Project Overview
Forss Wind Farm (Extension) is a 5.2 MW onshore wind project in Scotland. The applicant or operator on record is Renewable Energy Systems (RES). It is recorded as operational since July 2007. The determining authority is Highland, reference 01/00380/FULCA.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
| Capacity (MW) | 5 MW |
π Grid Connection & Infrastructure
π’ Development & Ownership
| Developer | Renewable Energy Systems (RES) |
| Owner / operator | Renewable Energy Systems (RES) |
| Year consented | 2006 |
| Construction started | 2007 |
| Commissioned / target | 2007 |
| Location | Ex Navy Base Forss, Dounreay Thurso Caithness, Highland, KW14 7YB |
| Region | Scotland |
| Coordinates | 58.6023591Β°N, 3.6881358Β°W |