π Project Overview
Fields Farm (Agden) is a 5 MW solar farm project in North West. The applicant or operator on record is Lightsource Renewable Energy. It is recorded as operational since February 2017. The determining authority is Cheshire West and Chester, reference 15/03109/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
| Capacity (MW) | 5 MW |
π Grid Connection & Infrastructure
π’ Development & Ownership
| Developer | Lightsource Renewable Energy |
| Owner / operator | Lightsource Renewable Energy |
| Year consented | 2016 |
| Construction started | 2016 |
| Commissioned / target | 2017 |
| Location | Fields Farm, Agden Near Whitchurch, Cheshire, SY13 4RB |
| Region | North West |
| Coordinates | 52.995739Β°N, 2.7248413Β°W |