Chiplow is a 8.2 MW onshore wind project in Eastern. The applicant or operator on record is Blue Energy. It is recorded as operational since April 2016. The determining authority is King's Lynn and West Norfolk, reference 10/00883/FM.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
| Capacity (MW) | 8 MW |
π Grid Connection & Infrastructure
π’ Development & Ownership
| Developer | Blue Energy |
| Owner / operator | Blue Energy |
| Year consented | 2012 |
| Construction started | 2015 |
| Commissioned / target | 2016 |
| Location | Bewteen the villages of Bagthorpe, Barmer and Syderstone in North West Norfolk, Norfolk |
| Region | Eastern |
| Coordinates | 52.8568782Β°N, 0.6907598Β°E |