Altaveedan Wind Farm is a 17.9 MW onshore wind project in Northern Ireland. The applicant or operator on record is NTR PLC. It is recorded as operational since April 2017. The determining authority is Causeway Coast and Glens, reference D/2010/0356/F.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
| Capacity (MW) | 18 MW |
π Grid Connection & Infrastructure
π’ Development & Ownership
| Developer | NTR PLC |
| Owner / operator | NTR PLC |
| Year consented | 2013 |
| Construction started | 2015 |
| Commissioned / target | 2017 |
| Location | in the townlands of Shelton South, Aldorough, Altaveedan North, Altaveedan South and Turnavedog near Loughguile, Co Antrim, Co. Antrim |
| Region | Northern Ireland |
| Coordinates | 55.0846552Β°N, 6.2577505Β°W |